What is required to obtain Engineering Division approval of my building permit after a grading permit has been issued?

Answer

Prior to engineering approval of the building permit, either the required public improvements must be installed and accepted, or performance bonds in the amount of 150% of the construction cost for all public improvements must be submitted, accompanied by a unit price cost estimate approved by the Engineering Division.