Asphalt Overlay Plans for Week of November 8th

11/05/2010

City asphalt crews will be working in several areas Nov. 8th - 12th.

Below is information on overlay projects scheduled for the week of November 8th. For details on all overlay projects completed this year, see the In-House Pavement Improvements Projects link in the Transportation section of this website.

On Monday, November 8th, the asphalt crew will overlay Lakefront Drive. The crew will conduct spot repairs on South Garland Tuesday, November 9th. South Wheeler will be milled on Wednesday, November 10th in preparation for its overlay on Thursday, November 11th. Sutton will be milled on Friday, November 12th.

Traffic will move slowly in these areas.  Allow extra time and watch for workers and machinery.